Step 4

Placement of Backfill Material

Fill material should be approved by geotechnical engineer prior to placement to insure conformance with structural design requirements.

Fill materials for the reinforced zone are placed in the wall for one block level at a time (8” lifts).

The Verdura® system can accommodate loading from heavy construction equipment, and for large walls backfill is typically dumped with scrapers in the grid zone.